In Progress
Aliana Pickleball and Office Park
Progress Updates
Project Timeline

2026-09-15T00:00:00.000Z
Beam installation is in progress.
2026-09-12T00:00:00.000Z
600 yards of concrete poured.
2026-08-29T00:00:00.000Z
Another 700 yards of concrete poured.
2026-08-20T00:00:00.000Z
700 yards of concrete poured.
2026-08-10T00:00:00.000Z
Underground utility work completed.
2026-03-01T00:00:00.000Z
Clearing and surfacing phase is underway.