2026-09-15T00:00:00.000Z
2026-09-15T00:00:00.000Z

Beam installation is in progress.

2026-09-12T00:00:00.000Z
2026-09-12T00:00:00.000Z

600 yards of concrete poured.

2026-08-29T00:00:00.000Z
2026-08-29T00:00:00.000Z

Another 700 yards of concrete poured.

2026-08-20T00:00:00.000Z
2026-08-20T00:00:00.000Z

700 yards of concrete poured.

2026-08-10T00:00:00.000Z
2026-08-10T00:00:00.000Z

Underground utility work completed.

2026-03-01T00:00:00.000Z
2026-03-01T00:00:00.000Z

Clearing and surfacing phase is underway.