C-Store and Retail Center, Crosstimbers
Project Timeline

Interior flooring and paint work is in progress.
Exterior panel installation is in progress.

400 yards of concrete poured.
35000 gallons of underground fuel tank installed successfully.
250 yards of concrete poured successfully.
250 yards of rebar installed successfully.
Metal structure completed for both the building and roofing work is underway.

Metal structure is taking shape.
Metal structure is in progress of both the buildings.
This site continues to move forward with another successful concrete pour of 200 yards.
19,000 CMU Blocks Installation is in progress.
1st round of concrete poured of 300 yards.
Momentum is building at the site. Material for the metal structure has arrived, while underground utility prep is actively underway.
Prep for utility and concrete is underway.
Demolition and site cleanup are nearing completion. The existing structure has been largely removed.
Demolition of the existing structure is in progress.