C-Store and Retail Center, Crosstimbers
In Progress

C-Store and Retail Center, Crosstimbers

Progress Updates

Project Timeline

2026-08-13T00:00:00.000Z
2026-08-13T00:00:00.000Z

35000 gallons of underground fuel tank installed successfully.

2026-08-04T00:00:00.000Z
2026-08-04T00:00:00.000Z

250 yards of concrete poured successfully.

2026-08-03T00:00:00.000Z
2026-08-03T00:00:00.000Z

250 yards of rebar installed successfully.

2026-08-02T00:00:00.000Z
2026-08-02T00:00:00.000Z

Metal structure completed for both the building and roofing work is underway.

2026-06-25T00:00:00.000Z
2026-06-25T00:00:00.000Z

This site continues to move forward with another successful concrete pour of 200 yards.

2026-06-18T00:00:00.000Z
2026-06-18T00:00:00.000Z

19,000 CMU Blocks Installation is in progress.

2026-05-15T00:00:00.000Z
2026-05-15T00:00:00.000Z

1st round of concrete poured of 300 yards.

2026-05-06T00:00:00.000Z
2026-05-06T00:00:00.000Z

Momentum is building at the site. Material for the metal structure has arrived, while underground utility prep is actively underway.

2026-04-09T00:00:00.000Z
2026-04-09T00:00:00.000Z

Prep for utility and concrete is underway.

2026-04-03T00:00:00.000Z
2026-04-03T00:00:00.000Z

Demolition and site cleanup are nearing completion. The existing structure has been largely removed.

2026-03-17T00:00:00.000Z
2026-03-17T00:00:00.000Z

Demolition of the existing structure is in progress.