In Progress
C-Store and Retail Center, Crosstimbers
Progress Updates
Project Timeline
2026-08-13T00:00:00.000Z
35000 gallons of underground fuel tank installed successfully.
2026-08-04T00:00:00.000Z
250 yards of concrete poured successfully.
2026-08-03T00:00:00.000Z
250 yards of rebar installed successfully.
2026-08-02T00:00:00.000Z
Metal structure completed for both the building and roofing work is underway.
2026-06-25T00:00:00.000Z
This site continues to move forward with another successful concrete pour of 200 yards.
2026-06-18T00:00:00.000Z
19,000 CMU Blocks Installation is in progress.
2026-05-15T00:00:00.000Z
1st round of concrete poured of 300 yards.
2026-05-06T00:00:00.000Z
Momentum is building at the site. Material for the metal structure has arrived, while underground utility prep is actively underway.
2026-04-09T00:00:00.000Z
Prep for utility and concrete is underway.
2026-04-03T00:00:00.000Z
Demolition and site cleanup are nearing completion. The existing structure has been largely removed.
2026-03-17T00:00:00.000Z
Demolition of the existing structure is in progress.