Highway 290 Truck Stop in Hockley, Texas
In Progress

Highway 290 Truck Stop in Hockley, Texas

Progress Updates

Project Timeline

2026-07-24T00:00:00.000Z
2026-07-24T00:00:00.000Z

Building sign installation completed.

2026-06-08T00:00:00.000Z
2026-06-08T00:00:00.000Z

Both fuel canopies are now fully framed and roofed, transforming the site and bringing the project one step closer to completion.

2026-06-05T00:00:00.000Z
2026-06-05T00:00:00.000Z

Two 40,000-gallon fuel tanks successfully installed in one day.

2026-05-12T00:00:00.000Z
2026-05-12T00:00:00.000Z

Canopy steel framing completed at the site.

2026-05-08T00:00:00.000Z
2026-05-08T00:00:00.000Z

Interior work is actively in progress at the site as flooring and paint work have completed.

2026-05-07T00:00:00.000Z
2026-05-07T00:00:00.000Z

Installation of steel pillars for the canopy is underway.

2026-04-30T00:00:00.000Z
2026-04-30T00:00:00.000Z

Exterior tile work is complete and interior work is actively underway.

2026-04-14T00:00:00.000Z
2026-04-14T00:00:00.000Z

Exterior tile work is underway.

2026-03-30T00:00:00.000Z
2026-03-30T00:00:00.000Z

Exterior panels and glass work are underway while interior paint work is underway.

2026-03-05T00:00:00.000Z
2026-03-05T00:00:00.000Z

Front sheathing finished, with siding and interior structure progressing on site.

2026-02-17T00:00:00.000Z
2026-02-17T00:00:00.000Z

Structural framing is actively progressing.

2026-01-19T00:00:00.000Z
2026-01-19T00:00:00.000Z

Decking work is underway.

2025-12-21T00:00:00.000Z
2025-12-21T00:00:00.000Z

350 yards poured overnight to stay on schedule. Deadline met.

2025-12-11T00:00:00.000Z
2025-12-11T00:00:00.000Z

Water pond construction completed. One more milestone checked.

2025-11-22T00:00:00.000Z
2025-11-22T00:00:00.000Z

From dusk to dawn, our crew kept the momentum going. Deadline met.

2025-11-07T00:00:00.000Z
2025-11-07T00:00:00.000Z

Crews are pouring concrete overnight to keep the foundation schedule moving.

2025-11-03T00:00:00.000Z
2025-11-03T00:00:00.000Z

Excavation and trenching are nearly finished, with utility lines being installed ahead of the concrete pour.

2025-10-23T00:00:00.000Z
2025-10-23T00:00:00.000Z

Clearing and early earthwork are in progress as the crew begins shaping the site for foundation and utility installation.