New Territory Community Center
In Progress

New Territory Community Center

Progress Updates

Project Timeline

2026-07-03T00:00:00.000Z
2026-07-03T00:00:00.000Z

HVAC, ceiling panels, and lighting installation are progressing together as the interior build-out continues.

2026-06-21T00:00:00.000Z
2026-06-21T00:00:00.000Z

HVAC progress continues with AC ductwork and vent installation underway, preparing the facility for efficient airflow, comfort, and long-term performance.

2026-05-30T00:00:00.000Z
2026-05-30T00:00:00.000Z

Ceiling lighting has been installed in the hall area, marking another key milestone as interior finishes continue to progress.

2026-05-29T00:00:00.000Z
2026-05-29T00:00:00.000Z

Floor tiling installation is currently underway, bringing durability, functionality, and a refined finish to the interior space.

2026-05-24T00:00:00.000Z
2026-05-24T00:00:00.000Z

Tile work on the walls underway.

2026-05-16T00:00:00.000Z
2026-05-16T00:00:00.000Z

Major interior milestones continue with active progress on hood, duct, electrical, and paint installation.

2026-05-15T00:00:00.000Z
2026-05-15T00:00:00.000Z

Level 5 wall finish underway.

2026-05-02T00:00:00.000Z
2026-05-02T00:00:00.000Z

Concrete work exceeding 100 yards has been completed across interior and exterior areas. Electrical and insulation work are in progress.

2026-04-09T00:00:00.000Z
2026-04-09T00:00:00.000Z

Paint for ceiling and some walls has been completed.

2026-03-05T00:00:00.000Z
2026-03-05T00:00:00.000Z

Interior metal framing is underway.

2026-03-02T00:00:00.000Z
2026-03-02T00:00:00.000Z

With demolition complete and debris removed, the team has transitioned to interior wall construction.

2026-02-10T00:00:00.000Z
2026-02-10T00:00:00.000Z

The project begins with controlled interior demolition and professional debris removal.