New Territory Community Center
Project Timeline

HVAC, ceiling panels, and lighting installation are progressing together as the interior build-out continues.

HVAC progress continues with AC ductwork and vent installation underway, preparing the facility for efficient airflow, comfort, and long-term performance.

Ceiling lighting has been installed in the hall area, marking another key milestone as interior finishes continue to progress.
Floor tiling installation is currently underway, bringing durability, functionality, and a refined finish to the interior space.

Tile work on the walls underway.
Major interior milestones continue with active progress on hood, duct, electrical, and paint installation.

Level 5 wall finish underway.
Concrete work exceeding 100 yards has been completed across interior and exterior areas. Electrical and insulation work are in progress.
Paint for ceiling and some walls has been completed.
Interior metal framing is underway.
With demolition complete and debris removed, the team has transitioned to interior wall construction.
The project begins with controlled interior demolition and professional debris removal.