Highway 99 Truck Stop in Baytown, Texas
In Progress

Highway 99 Truck Stop in Baytown, Texas

Progress Updates

Project Timeline

2026-07-03T00:00:00.000Z
2026-07-03T00:00:00.000Z

Steady progress continues as exterior finishes and interior build-out advance across the site.

2026-05-12T00:00:00.000Z
2026-05-12T00:00:00.000Z

Another milestone locked in. Canopy Steel framing is complete and the site continues to take shape.

2026-05-11T00:00:00.000Z
2026-05-11T00:00:00.000Z

This site has reached a major construction milestone with the completion of the primary building structure and installation of the fuel station canopy.

2026-04-04T00:00:00.000Z
2026-04-04T00:00:00.000Z

Metal framing is now underway at the site.

2026-02-22T00:00:00.000Z
2026-02-22T00:00:00.000Z

Preparing for another concrete pour.

2026-02-17T00:00:00.000Z
2026-02-17T00:00:00.000Z

When the schedule demands it, we deliver. 600 yards poured on time.

2026-02-13T00:00:00.000Z
2026-02-13T00:00:00.000Z

1,600 yards of concrete placed with precision.

2026-01-30T00:00:00.000Z
2026-01-30T00:00:00.000Z

1000 yard of concrete pour is underway.

2025-12-16T00:00:00.000Z
2025-12-16T00:00:00.000Z

Water pond construction complete at the Baytown Truck Stop.

2025-11-23T00:00:00.000Z
2025-11-23T00:00:00.000Z

Site prep and land clearing are in progress as we kick off another build with precision and planning.