In Progress
Truck Stop in Splendora, TX
Progress Updates
Project Timeline
2026-10-02T00:00:00.000Z
32000 and 2000 gallon of underground tanks installed.

2026-09-15T00:00:00.000Z
Metal structure is in progress.
2026-08-17T00:00:00.000Z
700 yards of concrete poured.
2026-08-08T00:00:00.000Z
250 yards of concrete poured successfully.
2026-07-30T00:00:00.000Z
Successfully completed 250 yards of concrete pour.
2026-07-21T00:00:00.000Z
Storm pipe installation is progressing while the site is being prepared for the next concrete pour.
2026-07-08T00:00:00.000Z
our crew successfully poured 200 yards of concrete while underground utility installation continued across the site.
2026-07-02T00:00:00.000Z
The raw land has been cleared, underground utilities are underway, and the water detention pond is taking shape.